Say to Sydney's
new international airport.

SKIP INTRO

0% played

Airside Civil and Pavement Works

Airside Civil and Pavement Works

The Airside Civil and Pavement works package (ACP) was awarded to the CPB ACCIONA Joint Venture in September 2021. This package involves the design and construction of the airside services and utilities which includes runway and taxiway pavements, aircraft pavement markings, airside roads, surface water drainage, aeronautical ground lighting systems, airside security fence and landscaping.     

The ACP package will include the construction of:

  • a 3.7-kilometre runway
  • access and exit taxiways and four rapid exit taxiways (RET) pavements
  • parallel taxiway pavements and aircraft isolation pad
  • an aeronautical ground lighting system (including related substation buildings) for CAT IIIB operations. This will allow Western Sydney International to operate safely in foggy conditions
  • perimeter roads and airside roads
  • security fencing, including civil works for services such as CCTV, lighting, communications and power.

 

What's happening?

 

September 2023 - November 2023

 

 

Over the past three months, the project team has:

  • Progressed works on the aeronautical ground lighting infrastructure.
  • Installed three prefabricated substation buildings and commenced commissioning.
  • Completed the building structures for both airfield lighting and equipment rooms (ALERs) and commenced commissioning.
  • Energised one ALER and one substation.
  • Continued construction of the runway and taxiways in all sections.

 

Over the next three months, the ACP project will continue to develop. Work will include commencing asphalt placement on the runway and taxiways, completing the concrete pavement on the taxiways, progressing the cabling for the aeronautical ground lighting, and installing utilities infrastructure. 

Airside Civil and Pavements Site

 

Airport Construction Update - September 2023

Airport Construction Update - July 2023 

Airport Construction Update - March 2023

Airport Construction Update - December 2022

Airport Construction Update - October 2022

Airport Construction Update - July 2022

WSA and its contractors are committed to keeping the community and  stakeholders informed about the project as it progresses. We welcome your feedback on this project and our other activities. Please contact our community team on the details below. 

 

Construction work hours

Standard work hours:

  • Monday to Friday: 7am - 6pm
  • Saturday: 8am - 1pm

 

Out of hours (OOH) work: We will consult and notify impacted residents prior to working outside of standard construction hours.

 

Contact details  

If you have any questions, or would like to provide feedback about the works, please contact the Community Engagement team: 

  • 1800 972 972  
  • info@wsaco.com.au  

For any procurement enquiries, please contact The CPB Acciona Joint Venture:

For any employment enquiries, please contact The CPB Acciona Joint Venture:

  • wsabe.employment@cpblljv.com.au